Environmental Representative for the Tomago 330kV Substation augmentation project.

Pre-Construction:

  • Compiled a monitoring and audit checklist against the conditions of approval
  • Reviewed principle contractor’s CEMP and any other environmental plans and advised TransGrid as to their suitability
  • Inducted contractor staff at possession of site hand-over meeting regarding environmental aspects of the project

Construction:

  • Undertook site monitoring inspections to verify compliance with conditions of approval, CEMP and environmental legislation particularly during:
    • Vegetation Clearing
    • Bulk earthworks
    • Civil and steel works
    • Building works
    • Electrical works
    • Transmission line connections (incl. earthworks for footings)
    • Commissioning of the substation
    • Site remediation and landscaping
  • Undertook random audits of the site and the contractor’s EMS
  • Prepared site audit reports and incident reports
  • Prepared a final report for the site, which included a list of outstanding, ongoing or future environmental management issues.

Key Aspects

Environmental Representative for the Tomago 330kV Substation augmentation project.

Completed inspections and formal audits to verify compliance with conditions of approval, CEMP and environmental legislation.